Spry Bridge

Abutment Rebar: 

Heavy reinforcing went in at each abutment. Check out the #11 at the nosing.

Casting Girders:

Pre-pour rebar inspection @ Bexar Concrete for the 100’ I-Girders.

Setting Girders:

Austin Crane Service helped us set the I-Girders in place. The clearances on each end were absolutely perfect.

Overhang Brackets:

Starting the Overhang Bracket install that will allow for the deck forms to be constructed.

Pouring Deck:

Another beautiful day, and lots of concrete poured!!